“The quality of workmanship is excellent and completed in a timely fashion. We have a good working relationship with Stave-con and would not hesitate to use them on any of our schemes.”
Client:
Client:
Location:
Duration:
Value:
Role:
The site was home to a derelict school which was segregated and demolished during the first 24 weeks of our programme. This reduced on-site space and posed logistical challenges for material storage and working areas which was mitigated using more just-in-time deliveries and renting adjacent land to site our compound, welfare and car parking.
Our work included two Section 278 highway bellmouths at opposite ends of the site connected by 400m of Section 38 adoptable estate roads and footways along with shared drives.
We constructed new adoptable Section 104 foul and surface water drainage, up to 450mm diameter with 144m3 of below ground attenuation and plot groundworks for 60 semi-detached and terraced 2-4 bed houses.
The topology was steeply sloping which required the construction of 1362m of retaining walls up to 5m high, including a 129m long x 5m high Tobermore system with concrete backfill.
“The quality of workmanship is excellent and completed in a timely fashion. We have a good working relationship with Stave-con and would not hesitate to use them on any of our schemes.”
“I have been extremely pleased with their ability to manage to deliver to our programmes and to an exceptionally high standard. Their effective on and off-site supervision and quality processes has played a key part in their delivery.”
“Stave-Con worked extremely very well within the programmed timescale putting Health and Safety first with no problems settling accounts and their customer care is excellent towards the road users and the residents of Sandwell.”
“Stave-Con’s expertise in both residential groundworks and Section 278 highway work gave us confidence to appoint them for both the civils and groundworks elements of the project, which helped to simplify communications and the coordination of works during the delivery of this scheme.”
“Their undertaking of the work has been exemplary and it was pleasing to see the Section 278 works delivered within programme and budget. I would have no hesitation in recommending them and have every confidence in appointing Stave-Con to future similar schemes.”
“We found their team to be collaborative, proactive and professional throughout including their workmanship, H&S, management of stakeholders and reduction of disruption on the local area. I would have no hesitation in recommending them and have every confidence in appointing Stave-Con to future highways and groundworks projects.”